On
this page we comment on some common contracts topics:
Exclusion
Clauses
Repudiatory
Breach and Material Breach of Contract
Best
Endeavours, Reasonable Endeavours
Interest
on Late Payments
Preferred
Supplier / Exclusive Supplier
Force
Majeure

Exclusion
clauses can take a variety of forms, such as for example excluding
categories of loss (eg loss of profits, loss of business, damage
to goodwill) to imposing conditions for making claims (eg procedures
or time limits) and financial limits to overall liability.
To
exclude liability for indirect or consequential loss
leaves the defaulter exposed to the full legal responsibility
for direct loss ie loss which flows naturally
from the breach without other intervening cause and independently
of special circumstances.
The
Unfair Contract Terms Act 1977 (UCTA) will apply to a contract
if either one party is a consumer or it is on written
standard terms. If either case a term which excludes
or limits liability for a breach is only valid to the
extent that the exclusion or limitation is reasonable.
The invalid the term must be fair and reasonable having regard
to the circumstances known to the parties when the contract was
made and (2) to those that the parties ought to have known at
that time.
UCTA
sets out in a schedule some guidelines for assessing reasonableness,
which refer to:
1...Bargaining
strength of the parties.
2...Inducements
to agree.
3...Whether
the goods were adapted to the particular order.
4...Whether
at the time of the contract it was reasonable to consider
that compliance with the exclusion or limitation would
be practicable.
5...Whether
the customer knew about the existence of the exclusion
clause, or ought to have known about it.
|
The
schedule applies specifically to contracts for goods and hire
purchase agreements, although the courts have used it as a guide
for assessing reasonableness in other contracts as well.
“Standard
terms of business” will include a contract which is based
on one party’s standard terms but the final form of which
is the result of a negotiation. It may be reasonable to exclude
or limit liability for one claim which the innocent party may
have upon a breach by the other party, but a parallel claim against
the defaulter is not excluded. The wording in these clauses is
interpreted strictly and they therefore require careful drafting
if they are to provide the protection that the contracting party
seeks. Protection is a matter of balance between looking after
the potential defaulter and overdoing the limitation such as to
render the whole clause unreasonable. If an innocent party is
left with no compensation rights at all in the face of a significant
default by the other party, then the clause is likely to be invalid.
Clauses
that exclude a liability, as opposed to limiting it, are looked
at with greater scrutiny by the courts. If the clause effectively
shuts out any claim for a fundamental breach, it is likely to
be held to be unenforceable.
If
a clause might be considered by the courts to be unreasonable
it is wise to take steps to draw the attention of the other contracting
party to it before the contract is entered into.
Further,
it is sensible to have separate exclusions clauses addressing
particular risks so as to minimise the possibility of unlimited
exposure in the event of a single exclusion clause being declared
invalid.
The
fact that a party is required to have insurance cover up to a
certain figure does not mean that any limitation of liability
below that figure is unreasonable.
All
attempts to exclude or limit liability for death or personal
injury (which includes food poisoning) are invalid and
unenforceable.

This
question arises frequently when an innocent party is considering
what options it has. There has been little guidance from the courts
over the years.
Under
general law a party to a contract is entitled to terminate the
contract if the other party has committed a repudiatory
breach ie, that other party has done something that is incompatible
with continued existence of the contract. Thus the breach must
be of a main condition of the contract (as opposed to a breach
of a warranty) or otherwise so serious as to deprive the
innocent party of the whole benefit of the contract.
This
requires careful assessment by the innocent party before it attempts
to terminate the contract. Getting it wrong may mean the innocent
party itself is in repudiatory breach and liable for damages.
Written contracts often provide a specific right to terminate
if the other party has committed a material breach. A material
breach may not be as serious as a repudiatory breach; materiality
has to be assessed in the context of the contract and on the impact
on the innocent party. In the case of non-payment of
money, the amount must not be trivial and the reason for non-payment
must not be as a result of mistake or understanding.
Importantly,
the fact that the contract has become economic for the defaulter
or that continuation of it would force it into insolvency is not
a defence.

Obligations
to use best endeavours or reasonable endeavours appear in a variety
of commercial contracts. What do these phrases mean?
“Best
endeavours” require a party to take steps which
a prudent and determined man acting in his own interests and anxious
to achieve the particular results would take even if that required
him to incur expense. The board must ask how far would a reasonable
and prudent board of directors go to achieve that aim ? They are
not required to incur financial ruin or undermine their commercial
goodwill; they can have regard to cost and the degree of difficulty
when deciding what practical steps to take.
“Reasonable
endeavours” is at the lowest end of the spectrum.
Only one reasonable course need be taken, without resorting to
take any other optional ones. The party is entitled to take account
of all commercial considerations, as well as the cost, the practicalities
and the chances of achieving success. It does not have to sacrifice
it commercial interests or act to its disadvantage. If however
the contract specifies certain minimum action then this has to
be taken by the party, irrespective of the impact on its commercial
interests.
“All
reasonable endeavours” means that the party must
continue its efforts until doing so would amount to repetition.
It is not as stringent as best endeavours.
A
recipient of a “reasonable endeavours” might well
wish to push for something more, including specific steps to be
taken. Whichever expression finds its way into the contract, an
endeavour does not amount to a guarantee of a particular outcome.

If
parties to a commercial contract have included a “substantial
remedy” for late payment, then that will regulate what happens
upon payments being delayed.
For
the rest, the Late Payment of Commercial Debts (Interest) Act
1998 will come to the rescue of creditors, ahead of commencing
court action for payment, and prove to be expensive for debtors.
The Act entitles the creditor (1) to levy an administration charge
for chasing a late payment and (2) to charge interest at the rate
prescribed.
(1)
Administration charge
This is available according to the size of the debt, as follows:
|
Size
of unpaid debt
|
Sum
to be paid to the creditor |
Up
to £999.99
|
£40.00 |
£1,000.00
to £9,999.99
|
£70.00 |
£10,000.00
or more
|
£100.00 |
(2)
Interest
The late payment interest rate, which is fixed for a six-month
period. is the reference rate + 8%. The fixed-reference periods
are:
|
|
The
six month period
|
The
Bank of England base rate on 31st December will be the
reference rate for:
|
1st
January to 30th June
|
|
The
Bank of England base rate on 30th June will be the reference
rate for:
|
1st
July to 31st December
|
| Period
|
Reference
Rate |
Interest
Rate (Reference Rate plus 8%) |
1st
July - 31st December 2008 |
5% |
13% |
|
1st
January - 30th June 2008
|
5.5% |
13.5% |
|
1st
July - 31st December 2007
|
5.5% |
13.5% |
|
1st
January - 30th June 2007
|
5.0% |
13% |
1st
July - 31st December 2006 |
4.5% |
12.5% |
|
1st
January - 30th June 2006 |
4.5% |
12.5% |
|
1st
July - 31st December 2005 |
4.75% |
12.5% |
1st
January - 30th June 2005 |
4.75% |
12.5% |

A
service provider will frequently wish to be appointed as an exclusive
supplier to its customer, while the customer may wish to retain
the liberty of engaging other suppliers for the same or similar
services. Sometimes the parties compromise by agreeing that the
supplier has “preferred” status. What does that expression
mean?
It
might for example mean that the supplier has to be offered the
first opportunity to supply the service and that the customer
will not obtain the services from other suppliers until the contracted
supplier had been offered a reasonable opportunity of meeting
the requirements and had failed to do so. But this is to impute
a good deal of interpretation into the expression. It could be
argued that a preferred supplier is merely one with whom the customer
has decided that it is prepared to deal, i.e. that “preferred”
simply means “approved”, with no attendant preference
or indeed exclusivity.
It
would be as well for the parties to spell out precisely what is
meant, in completely unambiguous terms.

The
function of a force majeure clause is to relieve a contracting
party, if he fails to perform his contractual obligations, from
being liable for breach of contract when the cause of the failure
is some event or circumstance out of his reasonable control. A
service provider, for example, would be at risk of damages claims
and indeed a termination of his contract even though he was ready
and willing to perform his services but was prevented from doing
so by some external event.
Some
force majeure clauses set out non-exhaustive lists of events or
circumstances outside of a party’s reasonable control, such
as weather conditions, fire or other damage to premises, shortages
of raw materials, labour disputes in their own supply chain etc.
Sometimes a receiver of the services will seek to exclude certain
events which would otherwise be generally understood as being
outside of the defaulter’s reasonable control. This is either
an aspect of risk sharing or in order to impose upon the service
provider the responsibility of either reducing the risk in that
area or otherwise taking on the responsibility of making plans
to circumvent such events.
A
force majeure clause is not a protection against rising costs
of providing the service. If the contract has become uneconomic,
it is still capable of being performed by the service provider.
The service provider must incorporate specific language into the
contract to deal with the risk of it becoming uneconomic.
Top
of page
|