
What
is it?
Arbitration
is a form of alternative dispute resolution. It has been referred
to as litigation without wigs.
Some
commercial contracts contain an alternative to litigation and
offer the parties arbitration. Arbitration clauses confer jurisdiction
on an individual or group of individuals, namely the arbitrators
who determine the issues in dispute. The rules of the fight may
also be incorporated into the agreement such as for example the
Construction Industry Model Arbitration Rules. The different rules
require their own consideration and too often at the point of
drafting the contract their proper scrutiny is overlooked. The
arbitration process can be very effective when used by experienced
practitioners willing to agree the rules and before a respected
and able arbitrator with knowledge of the subject matter in dispute.
The advent of adjudication albeit supposed to produce only a temporarily
binding outcome has in fact caused a huge decline in the number
of domestic arbitrations as the parties often accept the adjudicators
decision as final.
International
Disputes
Internationally
arbitration is however widely used as it provides a nationally
impartial arbitrator to an international dispute and the awards
made are readily enforceable in over 130 jurisdictions as a result
of the 1958 New York Convention. Great care must be taken in considering
choice of law for the arbitration and its seat as the seat of
the arbitration will govern the procedural law to be applied.
The
Arbitration Act 1996 (‘the Act’) was devised to restore
confidence in the arbitration process by providing an impartial
tribunal that would without unnecessary delay or expense bring
about the fair resolution of disputes.
The
Origins of the Arbitration Act
The
Act which came into effect in 1998 restricts the courts intervention
and gives the arbitrator increased powers.
In
summary, there are three sets of powers established by the Act:
‘Mandatory’
provisions - these deal with the immunity of the arbitrator, appeals
provisions, the general duties of the parties and the tribunal,
enforcement and the liability of parties for fees and expense
of arbitrators.
‘Default’
provisions - unless the parties agree otherwise, an arbitrator
will automatically be able to order claimant to provide security
for costs, give directions in relation to inspection and preservation
of property and direct a party or witness should be examined on
oath.
‘Optional’
provisions - these are provisions, which the parties can choose
to incorporate by agreement. Section 39 of the Act provides an
example of it. Under it, an arbitrator can make provisional arrangements
for interim payments but only if the parties agree to the arbitrator
having that power. There are many different arbitration clauses.
‘Additional’
powers - Section 39 of the Act provides that an arbitrator has
the power to make a provisional order for the payment of money
or the disposition of property. These additional powers exist
only if the parties agree to the arbitrator having these powers.
In
many cases, the choice of default and optional provisions has
already been exercised. Very often arbitration clauses refer to
specific rules under which the arbitration is to be conducted
and those rules operate within the Act. Many of those specific
rules deal with the default and operation provisions of the Act.
The procedures adopted within arbitration tend to be flexible.
Those procedures are now matched by the Civil Procedure Rules
(‘CPR’). Indeed certain aspects of the CPR are now
being adopted by arbitrators not least in relation to offers to
settle and cost awards.
Areas
to be borne in mind when deciding whther to incorporate into a
contract
The
two particular areas need to be borne in mind when deciding whether
to incorporate this form of dispute resolution into contracts.
The
first problem is that if there is an arbitration clause, the court
has no jurisdiction to hear the claim unless the other party fails
to apply to the court for a stay to arbitration. Under the Act,
the court has no discretion and must order a stay unless it is
satisfied that the arbitration clause is null and void, inoperative
or incapable of performance. The net result of this is that any
part of an arbitration clause may insist on the dispute going
to arbitration and cannot any longer go to the court for a summary
judgment.
The
second issue relates to joinder of parties. Under the Act, the
only parties to a dispute can be the parties to the arbitration
contract. The effect of this is that if there are other parties
at fault relating to the contract, the parties to the arbitration
agreement will need to bring separate proceedings.

What
is it?
It
is a form of dispute resolution peculiar to the construction and
engineering sector brought in with effect from 1st May 1998 under
the Housing Grants, Construction and Regeneration Act 1996 (‘the
Act’). The aim of the legislation is to provide a quick
fix system for resolving disputes as and when they arise on site.
There have been at least 20,000 adjudications since 1st May 1998
and these have given rise to some 120 court decisions mostly concerning
the enforceability of the decision and in the vast majority of
those cases the courts have enforced the adjudicator’s decision.
What
your contract should provide?
A
party to a construction contract caught by the Act has the right
to refer a dispute to adjudication and the contract must provide
a procedure for doing so. Where it does not (i.e. the parties
fail to comply with just one aspect of the statutory requirements)
then the statutory procedure contained in the Government Scheme
for Construction Contracts (S1 1998 n.649) (‘the Scheme’)
will apply.
Every
construction contract must:
Enable
a party at any time to give notice of his intention to refer a
dispute to adjudication;
Provide a timetable for an adjudicator to be appointed and the
dispute to be referred to him within 7 days of the notice of intention;
Require
the adjudicator to reach a decision within 28 days of referral
(it is open to the parties to agree a longer period);
Allow
the adjudicator to extend the period for his decision by up to
14 days but only with the consent of the referring party;
Enable
the adjudicator to take the initiative in ascertaining the facts
and the law;
Impose
on the adjudicator a duty to act impartially; and
Provide
that the decision of the adjudicator is binding until final determination
by litigation or arbitration.
Adjudication
under the Scheme
Notice
of Intention to Refer to Adjudication
The
Notice of Adjudication is the beginning stage of adjudication.
The party who has not been paid or may have some other dispute
prepares a Notice of Intention to Refer to Adjudication and this
notice is served on every party to the contract. The notice must
set out briefly the following:
A
brief description of the dispute and the parties involved;
Details
of when and where the dispute arose;
The
nature of the remedy being requested; and
The
names and addresses of the parties to the contract
Selection
of an Adjudicator
This
may be specified in the contract or it may identify a nominating
body to which the parties should apply. If the contract is silent
and it is not possible to reach an agreement, the following are
some of the adjudicator nominating bodies who may be asked to
select an adjudicator.
Centre
for Dispute Resolution
Chartered
Institute of Arbitrator
Chartered
Institute of Arbitrators
Chartered
Institute of Building
Institute
of Chemical Engineers
Institute
of Electrical Engineers
Institute
of Civil Engineers
Technology
and Construction Court Solicitors Association
Technology
and Construction Court Bar Association
Royal
Institute of British Architects
Royal
Institute of Chartered Surveyors
A
fee will be payable to the nominating body to whom the Notice
of Intention to Refer to Adjudication should be sent. The nominating
body should appoint an adjudicator within 5 days of receipt of
the application.
The
Referral Notice
Once
the adjudicator is appointed, the referring party has 7 days in
which to send to him the Referral Notice. This document sets out
the basis of the claim and identifies the remedies sought. It
should be accompanied by all the documents in support of the case
upon which the referring party wishes to rely. At the same time
that the Referral Notice and supporting documents were sent to
the adjudicator, a copy should also be sent to the other party.
The
Response
Once
the Referral Notice has been received, the adjudicator usually
writes to both sides setting out when the other party should respond.
The Response should address every point in the Referral Notice
and clearly state the responding parties’ case.
The
Response should also have in support any documentation on which
the responding party intends to rely.
The
Powers of the Adjudicator
The
Scheme gives the adjudicator wide powers to reach a prompt decision.
Those powers include:
To
require the parties to provide documentation;
To
meet and question any of the parties and their representatives;
To
make site visits and inspection;
To
carry out tests;
To
appoint experts or such other assistants as he deems necessary
provided he obtained parties’ consent to do so;
To
require the parties to limit the length of written or oral submissions;
To
set a timetable for directions to be complied with;
To
open up, revise any decision taken or any certificate given under
the contract unless it states that such a decision or contract
is final and conclusive.
The
Decision
The
adjudicator has 28 days to reach his decision from receipt of
the Referral Notice or 42 days if the Referring party agrees.
His
decision should state whether any payment is due from either party
or specified period within which it is to be paid.
Under
the Scheme, the adjudicator does not need to give reasons for
his decision unless requested to do so. The giving of reasons
does increase costs but reasons given may assist the parties.
The decision is only an interim one and is therefore temporarily
binding on the parties until final determination by litigation
or arbitration unless the parties agree to accept it as a final
decision.
Adjudication
under Other Forms of Contract
In
standard form contracts printed since the Act came into force
include provisions in relation to adjudication will be included.
The procedure under these contracts is very similar to the Scheme.
It may have been changed so that an adjudicator is named in the
contract or the adjudicator nominating body is specified. It is
essential to consider the terms of each contract before considering
adjudication so that the procedures set out in the contract are
carefully adhered to.
Enforcement
of the Adjudicators Decision
The
Courts are required to uphold the adjudicator’s decisions
and will not go behind the adjudicator’s reasoning even
if it is wrong or there is an obvious error. The courts are required
to be satisfied that the adjudicator did not act outside of his
jurisdiction. Issues concerning this aspect abound.
If
the adjudicator’s decision is not complied with then it
is necessary to issue court proceedings and there is an expedited
court process that provides for a speedy judgment without a need
for a trial. Judgment is usually granted provided the adjudicator
has acted within his jurisdiction.
Costs
of the Adjudication
An
adjudicator will be paid by the parties based on the terms, which
he agrees with them. Care is required in deciding what he should
be paid. If the dispute is complex, then he may need expert assistance
or legal advice and provided he obtains the parties agreement,
the cost of obtaining that assistance or advice will be borne
by the parties. The terms and conditions of the adjudicator’s
appointment could be agreed between the parties in writing. These
commonly provide that the adjudicator’s fees and expenses
are shared equally between the parties. Depending upon the terms
of the contract in question, the adjudicator may have the power
to order either side to pay the whole amount of those costs when
he issues his decision.
Most
of the standard forms of contract provide that each party should
bear their own costs and that the adjudicator’s costs should
be borne equally by the parties unless the adjudicator directs
otherwise.
Subject
to the terms of the contract, the adjudicator can only order the
other side to pay the Referring Party`s legal costs if this has
been requested to do so in the Referral Notice and the Responding
Party also requests their costs in their response.
The
costs of legal representation to enforce an adjudication decision
are at the direction of the court. The court rarely refuses to
enforce such a decision and the usual order is that the party
against whom the award is to be enforced bears the costs of the
enforcement process.
The
subject of legal costs is a complex one for which specific legal
advice must always be taken in advance of deciding which process
to use.
|